The Byrne Green Federal Court House

7th and Market Street

Philadelphia Pa

General contractor: Keating Building Corp.

 

The James A. Byrne federal Courthouse and William J. Green Federal building complex located along Market & Arch streets

 between 6th and 7th streets just west of Historical Independence Mall. This 23-year-old building complex underwent a major renovation,

 which required the replacement of the entire masonry façade and restoration of curtain wall of the courthouse, repair and resealing windows,

 roof improvements, and penthouse and chimney repairs for both courthouse and federal building.

This work required a unique scaffold system to facilitate these improvements.  Eastern Scaffoldings design and erection schedule,

 along with its unique containment system was chosen as best suited for this

Particular application allowing work to continue with out delay year round.

 

 

The Byrne federal courthouse stands 22 stories high, housing courtrooms, judge’s chambers, jury rooms and prisoner

 holding areas . The original brick facade had cracked and weakened from settlement over time causing a

 safety hazard consisting of pieces of masonry falling to sidewalk below.

 

 

ESS installed a Heavy duty pedestrian protection bridge rated  @ 300lbs per square ft. along the footway on three sides of the

 building which allowed for full access as well as protection to all pedestrians below while the construction was underway.

 

   

 

A large steel I beam frame had to be fabricated and attached to the existing steel building columns through the fourth floor roof,

 which surrounded the building at the 5th floor to support the System scaffolding that rose to the top of the building 280’ high. Eastern

 also provided additional equipment and engineering for a monorail lifting and trolley system for New limestone installation

 at the top of the building, and 8th floor area around the entire building.  The scaffold had been designed specifically for this

application in mind in order to support the anticipated heavy masonry loads and loads imposed by high winds and foul weather.

Which allowed repairs to continue year round.

 

  

 

The Tower scaffold was wrapped in a custom weather protection, and debris netting designed to withstand wind gusts up to 70 miles per hour.

 In October 2001.The scaffold and containment was subjected to a continuous high winds averaging around 57 mph. for 2 days with only minor damage.

 

 

ESS also installed a heavy-duty platform approximately 14,000 square foot over 40’ high, along the entire west side of the building for staging

And storage of heavy Masonry equipment and materials.  Another smaller, lower, heavy-duty deck at the corner of 7th and Market supported 3 construction trailers.

 

 

As you can see in the picture above the location of the material lay down deck is directly over the exit ramp of the parking garage.

 This required the installation of heavy steel I beams over the exit ramp along the 7th street side of the parking garage in order to maintain

egress from under the large heavy-duty material lay down deck above.

 

Eastern Scaffolding successfully completed their portion of the project on January 25, 2002;

 Unfortunately our founder the late Richard Frabizio Sr. who had been personally involved in all aspects of the project had been battling cancer

 and never saw the completion. Rich passed away on June 13, 2001; he will be sadly missed by all of us at Eastern Scaffold.

 

 

PHILADELPHIA CITY HALL

 TRENTON STATE CAPITOL BLDG        CAPE MAY LIGHT HOUSE        

    UNIVERSITY OF THE ARTS    SIDE WALK PROTECTION PICTURES     

  MISC PICTURES            GENERAL INFORMATION       

LINCOLN MEMORIAL      CON-EDISON

    LINKS 

 

Contact us by e-mail